  Remediation of TCE-contaminated groundwater by a permeable reactive barrier filled with plant mulch (Biowall)
 
 
Titel: Remediation of TCE-contaminated groundwater by a permeable reactive barrier filled with plant mulch (Biowall)
Auteur: Lu, Xiaoxia
Wilson, John T.
Shen, Hai
Henry, Bruce M.
Kampbell, Donald H.
Verschenen in: Journal of environmental science and health. Part A, Toxic/hazardous substances & environmental engineering
Paginering: Jaargang 43 (2008) nr. 1 pagina's 24-35
Jaar: 2008-01
Inhoud: A pilot-scale permeable reactive barrier filled with plant mulch was installed at Altus Air Force Base in Oklahoma, USA to treat trichloroethylene (TCE) contamination in groundwater emanating from a landfill. The barrier was constructed in June 2002. It was 139 meters long, 7 meters deep, and 0.5 meters wide. The barrier is also called a Biowall because one of the mechanisms for removal of TCE is anaerobic biodegradation. This study aimed at evaluating the performance of the pilot-scale Biowall after its installation. Data from over four years' monitoring indicated that the Biowall greatly changed geochemistry in the study area and stimulated TCE removal. The concentration of TCE in the Biowall and downgradient of the Biowall was greatly reduced as compared to that in ground water upgradient of the Biowall, while the concentration of cis-DCE in the Biowall and downgradient of the Biowall was much higher than that observed upgradient of the Biowall. Over time, the concentration of vinyl chloride in the Biowall and downgradient of the Biowall increased. Dehalococcoides DNA was detected within and downgradient of the Biowall, corresponding to the observation that vinyl chloride was produced at these locations. Results from a tracer study indicated that the regional groundwater flow pattern ultimately determined the flow direction in the area around the Biowall. The natural groundwater velocity was estimated at an average of 0.060 ± 0.015 m/d.
Uitgever: Taylor & Francis
Bronbestand: Elektronische Wetenschappelijke Tijdschriften
 
 

                             Details van artikel 11 van 15 gevonden artikelen
 
<< vorige    volgende >>
 
 Koninklijke Bibliotheek - Nationale Bibliotheek van Nederland